Electric utility guide · PG&E

ADU Electrical Service with Pacific Gas and Electric (PG&E)

How to get a service upgrade, a new or separate meter, or a relocated service from Pacific Gas and Electric (PG&E) when you add an ADU, and what our electrical plans give you for that application.

Order ADU Electrical Plans About electrical plans

Who PG&E serves

Investor-owned utility providing gas and electric service across a large service area in northern and central California. Of the California places we cover, 267 are served mainly by Pacific Gas and Electric (PG&E), and together they issued 34,032 ADU building permits from 2021 through 2025.

How PG&E handles new and upgraded service

Pacific Gas and Electric (PG&E) handles new service, service upgrades and meter changes through its Your Projects portal. This is separate from the building permit, so start it as soon as the electrical load calculation shows what the ADU needs. The steps PG&E describes:

  1. Submit an application through Your Projects and upload required documents, including permits if applicable.
  2. PG&E assigns a dedicated Job Owner who contacts the applicant and reviews project details, documents and load details.
  3. Pay an engineering advance if the Job Owner says one is required.
  4. Express Connect only: PG&E performs a load assessment; if existing infrastructure is insufficient the project moves to the standard New Project process.
  5. Field meeting or job-site walkthrough if necessary.
  6. Engineering and design: PG&E reviews load requirements and system capacity, confirms meter location and service route, prepares construction drawings and a cost estimate.
  7. Review PG&E's construction documents, then sign and pay the contract (Your Projects or DocuSign); complete any easements or land requirements the Job Owner directs.
  8. Site readiness: customer completes required trenching and site work (call 811 before digging) and any agency or PG&E inspections; a new account is set up if the location has not previously had PG&E electric service.
  9. Schedule PG&E construction with the Job Owner; PG&E crews perform the work.
  10. Arrange for the local government agency to inspect the electric panel; once it passes, contact PG&E to schedule the meter connection (meter set and energization).

What PG&E asks for

  • Project scope and timeline
  • Blueprints or plans (floor plans, line drawings, site plans)
  • Load requirements / load sheets, including appliances or equipment to be installed
  • Photos (listed for Express Connect)
  • Permits, if applicable
  • Meter panel details such as rating, UL listing and location (exterior wall, readily accessible, 36 inches of clear working space)

Our ADU electrical plans include the NEC Article 220 load calculation, panel schedule and single-line diagram, which cover the load and equipment information on this list. Site-plan and service-location details come from your architectural set.

A separate meter for the ADU

PG&E offers 'adding a meter and/or service' for an ADU as a residential project type (Express Connect up to 320 amps, or the New Business 'Residential add meter' type). Electric Rule 18 states PG&E will furnish and meter electricity to each individual residential dwelling unit (with listed exceptions), and that, consistent with Gov. Code 66338, junior accessory dwelling units (JADUs: no more than 500 sq ft and contained entirely within a single-family residence) are not considered residential dwelling units and are not required to be separately metered or to have a separate address. The Greenbook says that when more than two dwellings or buildings (e.g., a primary home and ADUs) are on one lot, applicants must consult their PG&E Job Owner on acceptable service-termination and meter locations before wiring, and that PG&E normally provides one service per enterprise, premise or parcel, with listed exceptions.

Whether a separate meter makes sense depends on the load calculation, the existing service size and the cost of the utility work. See when a separate service is required instead of a subpanel.

Service requirements

Meter location, clearances and service equipment must follow Greenbook - TD-7001M Electric & Gas Service Requirements (2026 edition; publication 04/22/2026, effective 06/22/2026). We show the meter and service equipment on the electrical plan so the location can be confirmed with PG&E early.

Places PG&E serves that we cover

PlaceCountyClimate zoneADU permits 2021–25
San JoseSanta ClaraCZ 42,399
Santa MariaSanta BarbaraCZ 52,199
San FranciscoSan FranciscoCZ 31,354
OaklandAlamedaCZ 31,186
CampbellSanta ClaraCZ 41,097
SalinasMontereyCZ 3865
FremontAlamedaCZ 3637
BerkeleyAlamedaCZ 3548
LivermoreAlamedaCZ 12525
Santa RosaSonomaCZ 2497
San MateoSan MateoCZ 3484
Los GatosSanta ClaraCZ 4450
Santa CruzSanta CruzCZ 3446
MontereyMontereyCZ 3446
RichmondContra CostaCZ 3417
PiedmontAlamedaCZ 3409
Menlo ParkSan MateoCZ 3398
SaratogaSanta ClaraCZ 4387
San Luis ObispoSan Luis ObispoCZ 5386
DavisYoloCZ 12384
Los AltosSanta ClaraCZ 4384
SunnyvaleSanta ClaraCZ 4377
Redwood CitySan MateoCZ 3354
PacificaSan MateoCZ 3340
TracySan JoaquinCZ 12330
HaywardAlamedaCZ 3319
Mountain ViewSanta ClaraCZ 4317
NapaNapaCZ 2303
HillsboroughSan MateoCZ 3298
BakersfieldKernCZ 13296
Los Altos HillsSanta ClaraCZ 4277
ConcordContra CostaCZ 12276
FresnoFresnoCZ 13268
Castro Valley (unincorp.)AlamedaCZ 3263
StocktonSan JoaquinCZ 12259
South San FranciscoSan MateoCZ 3258
Grover BeachSan Luis ObispoCZ 5257
San LeandroAlamedaCZ 3236
MilpitasSanta ClaraCZ 4229
BurlingameSan MateoCZ 3221
Alamo (unincorp.)Contra CostaCZ 12219
ChicoButteCZ 11218
Pacific GroveMontereyCZ 3218
San BrunoSan MateoCZ 3213
Daly CitySan MateoCZ 3207
VacavilleSolanoCZ 12206
PleasantonAlamedaCZ 12199
WatsonvilleSanta CruzCZ 3196
ClovisFresnoCZ 13194
CupertinoSanta ClaraCZ 4191
NovatoMarinCZ 2188
AthertonSan MateoCZ 3184
VallejoSolanoCZ 3, 12178
Union CityAlamedaCZ 3172
AntiochContra CostaCZ 12171
San CarlosSan MateoCZ 3171
LafayetteContra CostaCZ 12171
SeasideMontereyCZ 3169
EurekaHumboldtCZ 1166
WoodlandYoloCZ 12164
East Palo AltoSan MateoCZ 4164
GilroySanta ClaraCZ 4162
San RafaelMarinCZ 2157
Pleasant HillContra CostaCZ 12152
El CerritoContra CostaCZ 3145
Walnut CreekContra CostaCZ 12139
MartinezContra CostaCZ 12131
Granite Bay (unincorp.)PlacerCZ 11131
NewarkAlamedaCZ 3130
BelmontSan MateoCZ 3128
DublinAlamedaCZ 12127
DanvilleContra CostaCZ 12126
PetalumaSonomaCZ 2124
Carmel-by-the-SeaMontereyCZ 3123
GuadalupeSanta BarbaraCZ 5122
PittsburgContra CostaCZ 12113
El Sobrante (unincorp.)Contra CostaCZ 3113
Mill ValleyMarinCZ 3112
Nipomo (unincorp.)San Luis ObispoCZ 5109
Paso RoblesSan Luis ObispoCZ 4108
AtascaderoSan Luis ObispoCZ 4107
SoledadMontereyCZ 3107
AuburnPlacerCZ 11105
MantecaSan JoaquinCZ 12103
Morgan HillSanta ClaraCZ 4103
WoodsideSan MateoCZ 3100
Morro BaySan Luis ObispoCZ 598
AlbanyAlamedaCZ 397
BrentwoodContra CostaCZ 1295
Half Moon BaySan MateoCZ 394
GonzalesMontereyCZ 392
EmeryvilleAlamedaCZ 389
GreenfieldMontereyCZ 488
ShafterKernCZ 1386
San PabloContra CostaCZ 385
Los BanosMercedCZ 1284
OrindaContra CostaCZ 1281
RossMarinCZ 281
CapitolaSanta CruzCZ 381
MarinaMontereyCZ 380
FairfieldSolanoCZ 1279
Arroyo GrandeSan Luis ObispoCZ 578
TiburonMarinCZ 378
RocklinPlacerCZ 1176
HollisterSan BenitoCZ 474
ArcataHumboldtCZ 174
PlacervilleEl DoradoCZ 1272
Aptos (unincorp.)Santa CruzCZ 371
MendotaFresnoCZ 1368
FairfaxMarinCZ 268
Monte SerenoSanta ClaraCZ 467
Corte MaderaMarinCZ 366
King CityMontereyCZ 465
West SacramentoYoloCZ 1264
San AnselmoMarinCZ 262
St. HelenaNapaCZ 262
Shingle Springs (unincorp.)El DoradoCZ 1262
SebastopolSonomaCZ 261
MillbraeSan MateoCZ 359
Foster CitySan MateoCZ 357
SonomaSonomaCZ 257
LarkspurMarinCZ 257
Mariposa (unincorp.)MariposaCZ 1257
San Lorenzo (unincorp.)AlamedaCZ 357
SausalitoMarinCZ 356
Ashland (unincorp.)AlamedaCZ 354
Portola ValleySan MateoCZ 353
San RamonContra CostaCZ 1251
El Dorado Hills (unincorp.)El DoradoCZ 1251
WindsorSonomaCZ 249
LincolnPlacerCZ 1146
LoomisPlacerCZ 1146
American CanyonNapaCZ 245
RiponSan JoaquinCZ 1245
BelvedereMarinCZ 344
Rohnert ParkSonomaCZ 243
PinoleContra CostaCZ 343
BeniciaSolanoCZ 1242
ArvinKernCZ 1342
Fort BraggMendocinoCZ 141
McKinleyville (unincorp.)HumboldtCZ 140
Bay Point (unincorp.)Contra CostaCZ 1239
Glen Ellen (unincorp.)SonomaCZ 238
OakleyContra CostaCZ 1237
Santa Ynez (unincorp.)Santa BarbaraCZ 537
Kentfield (unincorp.)MarinCZ 236
Copperopolis (unincorp.)CalaverasCZ 1236
LathropSan JoaquinCZ 1235
Scotts ValleySanta CruzCZ 335
Cherryland (unincorp.)AlamedaCZ 335
Newcastle (unincorp.)PlacerCZ 1133
Castroville (unincorp.)MontereyCZ 333
Templeton (unincorp.)San Luis ObispoCZ 433
BrisbaneSan MateoCZ 332
Nevada CityNevadaCZ 1132
Kensington (unincorp.)Contra CostaCZ 331
MaderaMaderaCZ 1330
Diablo (unincorp.)Contra CostaCZ 1230
Grass ValleyNevadaCZ 1129
Penryn (unincorp.)PlacerCZ 1129
MoragaContra CostaCZ 1227
CalistogaNapaCZ 227
Rodeo (unincorp.)Contra CostaCZ 327
Fairview (unincorp.)AlamedaCZ 327
MercedMercedCZ 1225
Palo Cedro (unincorp.)ShastaCZ 1125
Del Rey OaksMontereyCZ 324
Kenwood (unincorp.)SonomaCZ 224
ReedleyFresnoCZ 1323
Mendocino (unincorp.)MendocinoCZ 123
Suisun CitySolanoCZ 1222
DinubaTulareCZ 1322
Meadow Vista (unincorp.)PlacerCZ 1122
Yuba CitySutterCZ 1121
DixonSolanoCZ 1221
NewmanStanislausCZ 1221
Valley Springs (unincorp.)CalaverasCZ 1221
Murphys (unincorp.)CalaverasCZ 1220
Soquel (unincorp.)Santa CruzCZ 320
CotatiSonomaCZ 219
CloverdaleSonomaCZ 219
Oceano (unincorp.)San Luis ObispoCZ 519
Kelseyville (unincorp.)LakeCZ 219
San Martin (unincorp.)Santa ClaraCZ 418
Pismo BeachSan Luis ObispoCZ 517
FortunaHumboldtCZ 117
Cayucos (unincorp.)San Luis ObispoCZ 517
Cameron Park (unincorp.)El DoradoCZ 1217
Camino (unincorp.)El DoradoCZ 1217
Moss Beach (unincorp.)San MateoCZ 317
OakdaleStanislausCZ 1216
KermanFresnoCZ 1316
ParlierFresnoCZ 1316
Foresthill (unincorp.)PlacerCZ 1616
San Miguel (unincorp.)San Luis ObispoCZ 416
HerculesContra CostaCZ 315
RiverbankStanislausCZ 1215
SelmaFresnoCZ 1315
WintersYoloCZ 1215
ClaytonContra CostaCZ 1215
WillitsMendocinoCZ 215
Olivehurst (unincorp.)YubaCZ 1115
FowlerFresnoCZ 1314
Durham (unincorp.)ButteCZ 1114
ChowchillaMaderaCZ 1313
BuelltonSanta BarbaraCZ 513
FerndaleHumboldtCZ 113
YountvilleNapaCZ 213
LivingstonMercedCZ 1213
Guerneville (unincorp.)SonomaCZ 213
GustineMercedCZ 1212
SolvangSanta BarbaraCZ 512
Redwood Valley (unincorp.)MendocinoCZ 212
LemooreKingsCZ 1311
SangerFresnoCZ 1311
OrovilleButteCZ 1111
McFarlandKernCZ 1311
LakeportLakeCZ 211
Red BluffTehamaCZ 1111
Lamont (unincorp.)KernCZ 1311
San Andreas (unincorp.)CalaverasCZ 1211
Penngrove (unincorp.)SonomaCZ 211
WascoKernCZ 1310
San Juan BautistaSan BenitoCZ 410
Hopland (unincorp.)MendocinoCZ 210
Forestville (unincorp.)SonomaCZ 210
Cottonwood (unincorp.)ShastaCZ 1110
KingsburgFresnoCZ 139
AndersonShastaCZ 119
Bolinas (unincorp.)MarinCZ 39
Diamond Springs (unincorp.)El DoradoCZ 129
Penn Valley (unincorp.)NevadaCZ 119
Wallace (unincorp.)CalaverasCZ 128
El Granada (unincorp.)San MateoCZ 38
Montara (unincorp.)San MateoCZ 38
SonoraTuolumneCZ 127
EscalonSan JoaquinCZ 127
Discovery Bay (unincorp.)Contra CostaCZ 127
Esparto (unincorp.)YoloCZ 127
Los Osos (unincorp.)San Luis ObispoCZ 57
Byron (unincorp.)Contra CostaCZ 127
Shingletown (unincorp.)ShastaCZ 117
Acampo (unincorp.)San JoaquinCZ 127
Lower Lake (unincorp.)LakeCZ 27
Blue LakeHumboldtCZ 16
Boonville (unincorp.)MendocinoCZ 26
Forest Ranch (unincorp.)ButteCZ 166
Felton (unincorp.)Santa CruzCZ 36
Pine Grove (unincorp.)AmadorCZ 126
Pacheco (unincorp.)Contra CostaCZ 126
CorcoranKingsCZ 135
Rio DellHumboldtCZ 15
Orange CoveFresnoCZ 135
Sheridan (unincorp.)PlacerCZ 115
Crockett (unincorp.)Contra CostaCZ 125
Georgetown (unincorp.)El DoradoCZ 125
Mokelumne Hill (unincorp.)CalaverasCZ 125
Catheys Valley (unincorp.)MariposaCZ 125
Graton (unincorp.)SonomaCZ 25
Occidental (unincorp.)SonomaCZ 1, 25
Creston (unincorp.)San Luis ObispoCZ 45
Magalia (unincorp.)ButteCZ 165
Ben Lomond (unincorp.)Santa CruzCZ 35
Los Alamos (unincorp.)Santa BarbaraCZ 55
Hidden Valley Lake (unincorp.)LakeCZ 25
Stinson Beach (unincorp.)MarinCZ 35
Plumas Lake (unincorp.)YubaCZ 115

Sources

Summarized from Pacific Gas and Electric (PG&E)'s published pages. Utility processes, forms and rules change, so confirm the current requirements with PG&E (contact) before you apply.

Need ADU electrical plans for a PG&E service request?

We prepare the load calculation, panel schedule and single-line diagram the utility and the building department both review.

Start My Order