2025 Energy Code · Climate Zone 5

Title 24 Climate Zone 5: ADU Requirements

What the 2025 California Energy Code's prescriptive package requires for a new detached ADU in Climate Zone 5, and how those requirements change the MEP design.

Order MEP Plans + Title 24 About Title 24 reports

Where Climate Zone 5 is

Of the California places we cover, 16 are mostly in Climate Zone 5, across 2 counties: San Luis Obispo County, Santa Barbara County. Together they issued 3,590 ADU building permits from 2021 through 2025. Zones follow ZIP-code boundaries, so we confirm the zone from the project address before running the Title 24 report.

2025 prescriptive requirements for a new detached ADU

For a new detached ADU in Climate Zone 5, the 2025 prescriptive package sets these zone-specific targets.

WindowsU-factor 0.27 or lower; SHGC No limit; total area up to 20% of floor area
Attic, high-performance optionR-30 ceiling; below roof deck: Not required
Attic, ducts-inside optionR-30 ceiling plus radiant barrier; ducts and air handler in conditioned space
Framed wallsAssembly U-factor 0.048 or lower
Cool roofNot required
Whole-house fanNot required
Space heating and coolingHeat pump (other systems through the performance approach)
Water heatingHeat pump water heater; units of 500 sq ft or less, or one bedroom or fewer, have simpler options
Solar PVkW = (floor area x 0.585) / 1000 + 1.06; none required under 1.8 kWdc (about 1,265 sq ft or smaller for a single ADU)

An attached ADU or a garage conversion is an addition under the Energy Code, not new construction, so it follows the addition requirements instead. Solar PV is not required for additions.

Design temperatures across Climate Zone 5

The zone sets the energy targets, but the HVAC is sized from the local design temperature, and that varies inside a zone. Among the places we cover here, the 1% summer design temperature ranges from 76°F in Lompoc to 85°F in San Luis Obispo, and the coldest winter design temperature is 25°F in Santa Maria. That spread is why we run a Manual J for each address instead of using a zone-wide rule of thumb.

Places in Climate Zone 5

PlaceCountyElectric utilityADU permits 2021–25
Santa MariaSanta BarbaraPacific Gas and Electric (PG&E)2,199
San Luis ObispoSan Luis ObispoPacific Gas and Electric (PG&E)386
Grover BeachSan Luis ObispoPacific Gas and Electric (PG&E)257
LompocSanta BarbaraCity of Lompoc Electric Utility214
GuadalupeSanta BarbaraPacific Gas and Electric (PG&E)122
Nipomo (unincorp.)San Luis ObispoPacific Gas and Electric (PG&E)109
Morro BaySan Luis ObispoPacific Gas and Electric (PG&E)98
Arroyo GrandeSan Luis ObispoPacific Gas and Electric (PG&E)78
Santa Ynez (unincorp.)Santa BarbaraPacific Gas and Electric (PG&E)37
Oceano (unincorp.)San Luis ObispoPacific Gas and Electric (PG&E)19
Pismo BeachSan Luis ObispoPacific Gas and Electric (PG&E)17
Cayucos (unincorp.)San Luis ObispoPacific Gas and Electric (PG&E)17
BuelltonSanta BarbaraPacific Gas and Electric (PG&E)13
SolvangSanta BarbaraPacific Gas and Electric (PG&E)12
Los Osos (unincorp.)San Luis ObispoPacific Gas and Electric (PG&E)7
Los Alamos (unincorp.)Santa BarbaraPacific Gas and Electric (PG&E)5

Sources

Requirements shown are the 2025 prescriptive package (effective January 1, 2026) for newly constructed single-family buildings, which includes new detached ADUs. A performance (computer-modeled) approach can trade some items against others. Your Title 24 report confirms what applies to your project.

Need MEP plans and a Title 24 report in Climate Zone 5?

We prepare both from the same design, so the energy model and the equipment on the plans agree.

Start My Order